Thanks to the support of voters, Mendota Elementary School is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.
UPDATE FOR AUGUST 13, 2019
Completed for the week ending August 9, 2019
- Project is in Construction Documents phase.
- Weekly Design Consultants meetings being held at LSE.
- ICS walked the school to verify existing conditions of the school.
BUILDING PROJECTS
Academic and Program Improvements
• Rightsize kindergarten classrooms to meet state guidelines
• Handicapped accessibility improvements
• Build additions for grades 1-4 classrooms and renovate existing space for collaboration/small-group commons
• Addition of staff and visitor bathrooms
• Lab renovations
Building Maintenance Improvements
• Site improvements include concrete walks and paving
• Exterior improvements include roofing, tuck pointing, and sealants
• Interior finishes include flooring, stage partition, and gym equipment
• Electrical improvements include lighting
PROJECT TIMELINE
• Design and Planning: March 2019-September 2019
• Construction Phase: April 2020-August 2020
• Construction - Exterior Additions: Last Spring-Summer 2020
• Construction - Interior Renovations: Summer 2020
• Completion: Late August 2020