Thanks to the support of voters, Heritage E-STEM Magnet School is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.
UPDATE FOR AUGUST 13, 2019
Completed for week ending August 9, 2019
- Project is in design development phase.
- Weekly design meetings are being held at LSE Architects.
- Input for design of the existing pool area is being gathered from stakeholders.
BUILDING PROJECTS
Academic and Program Improvements
• Cafeteria handicapped accessibility improvements and removal of stage
• Commons area access improvements and renovations
• Music area improvements
• Media production lab renovations
• Meeting space renovation
• Addition/renovation of relocated performance/multi-purpose space with stage
Building Maintenance Improvements
• Site improvements include landscape, concrete walks, and fencing
• Exterior improvements include tuck pointing, sealants, soffit venting, and door hardware
• Interior finishes include doors, locker room lockers, elevator improvements, flooring and gym equipment
• Mechanical improvements include boiler and chiller plants, piping, and ventilation
• Electrical improvements include lighting and PA system
PROJECT TIMELINE
• Design and Planning: March 2019-November 2019
• Construction Phase: June 2020-August 2021
• Construction - Interior Renovations: Summer 2020, 2021
• Completion: Late August 2021