Henry Sibley High School
Logo: Henry Sibley High SchoolThanks to the support of voters, Henry Sibley High School is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.

BUILDING PROJECTS


Academic and Program Improvements

Site improvements include a multipurpose athletic facility with a new multisport turf field and track (high school football and soccer will move to Henry Sibley and Matson Field remains), baseball and softball dugouts, concessions, ticket booth, scoreboard, bleachers, and drainage improvements
Performing arts/music improvements to meet guidelines 
Auditorium enhancements
New swimming pool (replaces pool at Heritage)
Locker room renovations
Science renovations and improvements to meet guidelines 
Commons areas and access improvements
Modernization of art, family and consumer science, shop, and labs to create career and technical education spaces 
Creation of small group break-out spaces
Repurposing of existing meeting space
Improvements to exterior entry for handicapped access and plaza 
Renovations at school store, café, and collaboration space
Multipurpose expansion for health & fitness 
Specialist/office space renovations and expansions

Building Maintenance Improvements
Site improvements include parking lots, landscape, concrete walks, drainage, and fencing 
Exterior improvements include tuck pointing, sealants, and painting
Interior finishes include lockers, doors, elevator improvements, flooring, and gym flooring and equipment
Mechanical improvements include piping, equipment improvements, plumbing upgrades, and ventilation improvements 
Electrical improvements include lighting and public address system



PROJECT TIMELINES
Classrooms, music, science, indoor athletics, etc.
Design and Planning: June-December 2018
Construction: Late Spring 2019-Fall 2021 (phasing plans TBD by Fall 2018)

Multiuse Stadium
Design and Planning: June-December 2018
Construction: April/May-September 2019 (occupancy August 2019)

Swimming Pool
Design and Planning: June-December 2018 Construction: TBD

All Projects Complete: Late August 2021



CONCEPT DRAWINGS
Floor One  |  Floor Two (main)  |  Floor Three 
Site (exterior)



SUBCOMMITTEE MEMBERS

Hayley Ball
Janelle Christensen
Angela Corbett
Adam Crepeau
Daymond Dean
Cari Jo Drewitz
Bryson Halsey
Sean Hickey
Kirsten Huber
Aiden Jacobs
Tony Kienitz
Madeline Knoll
Ben Kusch 
Adrienne Meyers
Ron Monson
Gabe Monsour
Jen Olson
Tom Orth
Jaelyn Orth
Erica Ramisch
Greg Schmidt
Khadija Sharif 
Prentice Smith
Sue Soine
Cyd Vanderbeek
Dean Verdoes
Quintin Warford